| Before construction |
2004~2006 |
- Selection of the ITER construction site: Cadarache, France
- Preparation of the ITER Joint Implementation Agreement(JIA)
- Execution of ITA Tasks
- Establishment of legal and organizational system to promote the ITER Project
|
| Construction |
2007~2019
(First Plasma) |
- Creation of the design and manufacture technology basis for the ITER
- Agreement on Procurement Agreements(PAs) between IO and DAs and their implementation Manufacture of the procurement items
- Project process control and Quality management
- Delivery, supply, installation and on-site test of the procurement items and acquiring corresponding credit values
- Development and operation of ITER Korea Project Management System
|
| Operation |
2019~2037 |
- Participation in the operation of the ITER
- Experiment of burning plasma
|
| Deactivation |
2037~2042 |
- Deactivation of the ITER machine
|
| Decommissioning |
After 2042 |
- France, the host country responsible for the completion of decommissioning
- the related technology and information shared by the ITER Parties
|